| YEAR 2000 PROBLEM - ISRAEL (OVERVIEW, JANUARY 1999)
Terminology
The Y2K problem is referred
to also as the "Y2K Bug" or the "Millennium Bug". Although bugs are a matter
of personal taste, usage of the term "Millennium" here is somewhat misleading,
since the second Millennium is to end on December 31st, 2000 and not on
December 31st, 1999. Just a thought…
Background
The "Y2K Bug" is a threat
to all computer programs, even those in the most simple and trivial applications.
For decades, the year was represented by two digits: 1980 is "80", 1999
is "99" and 2000 is…
And there lies the problem:
for years, "99" was the code in computer systems for "error" and "00" may
not only produce negative results in calculations, but may also be completely
unknown to the computer system or may be interpreted as "infinity".
We had already experienced
many difficulties accessing certain Internet servers during the first days
of 1999. After checking with the home server and the destination server,
the conclusion was that the somewhere along the route, one of the servers
caused a problem and prevented us from accessing the destination. A simple
run of the program "tracert www.DESTINATION-NAME.com" revealed that communication
got stuck at around the 15th connection. This indicates how grave the problem
is since we depend on external service providers. Not only our home server
and destination server need to be Y2K compliant, but all 15 or more servers
in between. This certainly minimizes the feasibility of overall compliancy.
Israel Government
Already back on July 7th,
1996, the government of Israel decided that the Y2K problem should be addressed.
But, only in January 1998 a Y2K sub-committee, headed by MK (Member of
Knesset, Israel Parliament) Prof. Alex Lubotzky, commenced functioning.
The overall impression is that the problem had not been addresses adequately
and seriously enough until December 1998. However, In a television interview
given on January 9th, 1999 by Deputy Minister Michael Eitan, he stated
that the Emergency Economy Unit is to operate during the transition from
1999 to 2000. The Emergency Economy Unit is normally to operate in cases
of a military offensive actions against Israel or in other critical emergency
events. This demonstrates that the government does consider the Y2K problem
as a potentially acute one.
Ministry of Health
In February 1998, M.L.L.
software & Computers Industries Ltd. Completed a Y2K compliancy project
for the budgetary accounting system in 28 government hospitals.
Ministry of Defence
Reportedly (July 1998), all
civilian systems are to be compliant by the end of 1998.
Ministry of Finance
The project commenced in
September 1996. The Y2K budget in 1997 amounted to US$ 400,000 and 170
months of labor, in 1998 the budget amounted to US$ 230,000 and 104 months
of labor.
Ministry of Labor &
Welfare
Reportedly (May 1998), Binsoft
of the Kardan Group is to conduct the project for the National Insurance
Institute. The institute is to conduct two major tests in March and August,
1999.
Ministry of Transport
Reportedly (February 1998),
S.P.L. WorldGroup Israel won a tender for the vehicles and drivers Licensing
office. The project was reported as completed in August 1998.
Ministry of Infrastructure
S.C.H. Software Conversion
House of the Formula group is to conduct the project for Israel Lands Authority.
Ministry of Tourism
Tourism in year 2000 is certainly
facing a double challenge. According to the "Israel 2000 Administration"
the forecast is of 4 million pilgrims arriving to Israel during the years
1999-2001.
The Knesset (Israel Parliament)
Effective July 1998, Tescom
Software Systems Testing commenced analyzing the computer systems as the
first stage of the Y2K project.
The Postal Authority
The IT department commenced
the project that will include a nationwide network of 250 branches and
250 agencies. Expenditure in 1998 in the Y2K project amounted to US$ 1.4
million.
Israel Electric Corporation
Reportedly (May 1998) the
project is to be conducted by Formula Software Services and Tadiran Information
Systems using tools of Crystal Systems Solutions of the Formula Group.
The Project is to amount to US$ 9 million.
Reportedly (January 1999),
a strategic stock of 1.9 million tons of coal is to be accumulated in the
power stations towards the transition to year 2000, enough for 2.5 months
of electricity production.
Bezeq Telecommunication
Corporation
According to an agreement
of April 1997 the project is to be conducted by Formula Software Services
and Tadiran Information Systems.
Reportedly (May 1998) Kontahal
was chosen to analyze the switching and control systems.
The Airports Authority
Tadiran Information Systems
and Liraz Systems are conducting the project, amounting to US$ 6 million.
Mekorot Water Company
The project commenced in
1996 and was reported as completed in July 1998. A general testing of the
systems is scheduled to April 1999.
Magen David Adom in Israel
In July 1998, YAANA Systems
Ltd. was chosen to conduct the project for The Blood Bank.
Small-Medium Businesses
IBM Israel announced (Mid
January 1999) that it is offering small to medium businesses its support
service for Y2K compliancy. The service, for Microsoft, IBM and Novell
networks, is charged at US$ 24 per station.
Note: The overview is based
on public announcements and publications. |